Project Description

Project:  Droylesden Marina, Manchester
Main Contractor:  Watkin Jones

SDH Engineering were tasked with delivering this large project on a tight lead time.

The complete package consisted of 26 external walk out balconies, stainless steel and glass balustrade, 26 front Juliet balconies and rear terrace areas consisting of 45 metres of stainless steel and glass balustrade, window grills and internal stair balustrade.

We completed our duration of work within 10 weeks. We were able to achieve this with the dedication of our shop and site teams and the ability of our in-house design team, from through our detailed 3D CAD models, we were able to to pre order all glass required thus reducing lead time and enabling us to complete this project within the very tight time constraints.